When is a JIRA story displayed as a package in Can Do?

The stories are in JIRA (in the backlog) and also connected to an EPIC. The interface is activated, yet no package appears in Can Do.

Can Do requires start and end dates to create a package. These dates are assigned in JIRA in a Scrum project when a new Sprint is started. So you have to start a sprint and store a start (of the sprint) and an end there. When the story is dragged into that sprint, it appears as a package in Can Do.

In JIRA you can start as many sprints as you like, one after the other, so you can plan for the long term. This is not the classic agile method, but it works beautifully.