Time scale in the Project Planner App
How can the time scale be adjusted?
In the "View" tab there are four buttons to change the time scale. There is always an upper (coarse) and a lower (fine) scale. The buttons refer to the top view, the bottom view is always one step finer.
Any temporal text can be entered in the Period field. For example:
- January
- Quarter 2
- March to April
- Week 15 - December
Of course, an exact date can also be entered. Dates and periods can also be selected via the calendar symbol on the right. If you click on the calendar week, it is marked. In the upper view, you can also click on the month, then you see all months and can select long-term periods.