What is the “real effort” in Can Do
This field appears in some apps and is a mix of planned and reported expenditure
The real effort is
- the same as the planned expenditure, as long as NO time recording has been carried out yet (and the project has not been completed).
- if a time recording has been made, the real effort for this resource is
- equal to the reported expenditure for all days until the last time recording
- equal to the remaining expenditure for all days after the last time recording (during which the project is still ongoing)
- If the project was completed or time recording took place on the last day of the project, the real effort is equal to the reported effort