What is the “real effort” in Can Do

This field appears in some apps and is a mix of planned and reported expenditure

The real effort is

  • the same as the planned expenditure, as long as NO time recording has been carried out yet (and the project has not been completed).
  • if a time recording has been made, the real effort for this resource is
    • equal to the reported expenditure for all days until the last time recording
    • equal to the remaining expenditure for all days after the last time recording (during which the project is still ongoing)
  • If the project was completed or time recording took place on the last day of the project, the real effort is equal to the reported effort
The “real” efforts take into account the date of the last time recording, object status and feedback.